Formula needed for Project Management

Filed under: Project Management — mani @ 12:02 am

Formula
Time Mananagement PERT Expected Activity Duration(EAD) (P+4M+0)/6
Standard Deviation of Activity (P-O)/6
Variance of Activity ((P-O)/6)^2
Range of Activity EAD +/ SD
Total Float LS-ES or LF-EF
Cost Management Schedule Variance EV-PV
Cost Variance EV-AC
Schedule Performance Index(SPI) EV/PV
Cost Performance Index (CPI) EV/AC
Estimate At Completion (EAC) AC + BottomUp ETC
AC + (BAC-EV)
BAC/CPI
AC+((BAC-EV)/(BAC-AC))
To Complete Performance Index (TCPI) (BAC-EV / BAC-AC)
Estimate To Complete (ETC) EAC – AC
Variance At Completion (VAC) BAC-EAC
Communication Management Communication Channel N(N-1)/2
Risk Management Expected Monetary Value (EMV) P X I
Procument Management Point of Total Assumption (PTA) ((Ceiling Price – Target Price) / Buyer’s Share Ratio )) + Target Cost